Lead Time Forecast
Use Reporting → Manufacturing → Lead Time Forecast to estimate production time and compare scheduling results for make-to-order finished goods. The report evaluates item, variant, and packaging combinations and shows planned dates, routing, throughput, and scheduling cost information.
Start with a specific item and the package quantity you want to assess. A useful result has the expected variant and packaging, the right quantity and units, an OK status, and dates you have compared with your intended shipping date.
Set the scope of the forecast
Use these controls to define the calculation, then select Create report.
| Control | What to choose and check |
|---|---|
| Shipping Start Date | Your target shipping date. The initial value is 14 days ahead. The calculation uses this date minus the configured minimum production lead time as its scheduling starting point. It searches a 365-day horizon, so compare the returned dates with your target. |
| Item Name | Enter part of the finished-good item's name. This is required. Use a narrow name: the search takes up to 10 matching finished goods before retaining those with make-to-order procurement. |
| Variant Name | Optionally narrow the variants by text in their name. The name comparison ignores letter case. Variants marked inactive are excluded. |
| Quantity | Enter the number of packages to assess. The initial value is 5. Each packaging choice turns that count into an item quantity using its packaging quantity. Check the resulting Quantity and unit in the report. |
| Warehouse | Choose All or one of the active warehouses configured for manufacture replenishment. A specific warehouse restricts the scheduling comparison to that warehouse. |
| Group By | Choose Item by Work Center to compare returned work-center alternatives, or Warehouse, Work Center by Item to review results under their selected warehouse and work center. |
| Metrics | Choose All or the measures you want to inspect. Name, Quantity, Total Weight, and Status remain visible. |
An item needs an included variant and a packaging record that the report can resolve to produce a calculation line. A matching name alone does not establish that the item will appear.
For example, assume a packaging record contains 12 item units. An entered Quantity of 5 produces a calculation quantity of 60 item units for that packaging. This example illustrates the conversion; 12 is not a default packaging quantity.
Choose a view that fits the comparison
Item by Work Center is the initial view. It places variants and packaging beneath each item and adds metric columns labelled with the work-center name. The report includes the earliest-completing successful schedule and can add other fitted finished-goods work centers returned by the scheduling calculation.
Each work-center result includes the routing's calculation, with that center used for the finished-goods step. Read its lead time and cost as a result for that routing alternative, rather than the isolated workload or cost of one work center.
Warehouse, Work Center by Item nests the results by warehouse, work center, item, then variant and packaging. For each combination, the report keeps the successful warehouse schedule whose final planned end is earliest. With Warehouse set to All, this view therefore shows the selected result for each combination; it does not list every eligible warehouse alternative.
Group headers show averages of successful calculation lines for lead time, cost per unit, and the displayed margin indicator. Their counts and error statuses help you judge coverage. Read the child rows before using a group average to compare different packages or variants.
Read time, dates, and the supporting values
Use the timing columns together. They answer different planning questions.
| Information | How to interpret and check it |
|---|---|
| Lead Time (min) and Lead Time (hrs) | The sum of required work-center minutes returned for the routing's scheduled steps, also expressed in hours. This measures work demand. It does not measure the calendar interval between production dates. |
| Prod. Start and Prod. End | The earliest planned start and latest planned end across the routing's scheduled steps. Use these dates to assess when the calculation places the work. |
| First Ship | The same calculated date as Prod. End in this report. Review shipping requirements separately before making a delivery commitment. |
| Routing and BOM | The routing explanation and bill-of-material number returned for the combination. The routing tooltip adds the route, node count, and duration per item unit. Check these against the variant and packaging you intended to assess. |
| Output/Hr and Efficiency % | Throughput and efficiency returned for the finished-goods step. Inspect the throughput and lead-time tooltips to check the quantity, weight, units, and capacity figures behind the result. |
| Cost/Unit, Total Cost, Labor Cost, and Idle Cost | Planned scheduling costs and their reported breakdown. Cost tooltips show the quantity and component amounts used. Compare the same package quantity and routing alternative when reviewing costs. |
| Unit Price, Price/Weight, Total Weight, Cost/Weight, and Margin % | Supporting price, weight, and cost comparisons. Check variant price and weight inputs, including their units. Review Margin % alongside Unit Price and Cost/Unit with your costing owner before using it for pricing. |
Open the Lead Time (min) tooltip when a duration is unexpected. It breaks down the scheduled steps and shows their minutes, work centers, planned dates, and available throughput details. It also distinguishes the work-demand total from the calendar span, where production dates are available. Gaps between shifts or routing steps can make those two durations differ.
Check coverage before using the result
Begin with Status and Calculation Messages. Successful combinations show OK. An error row carries the calculation's message, while a group can show an error count with details in its status tooltip.
The summary's Data Coverage identifies the make-to-order items evaluated, calculation lines, errors, and work centers used. Its Lines with No Routing figure counts calculation errors, so read the actual messages before deciding that routing is the cause.
Summary averages exclude error lines. Summary totals add successful calculation lines. In Item by Work Center, those lines can include several alternatives for the same variant and packaging. Check for those alternatives before treating total cost or total weight as a production requirement.
Use Report Parameters to confirm the shipping date and packaged quantity, Manufacturing Infrastructure to review the listed warehouses and work centers, and Work Schedule to review the listed active shifts. These checks help explain the calculation's context; they do not replace checking the returned dates and row messages.
Investigate missing rows or errors
| What you see | What to check next |
|---|---|
| A request to write an item name | Enter Item Name and select Create report. |
| No expected item or variant | Narrow the item name, check that the item is a finished good with make-to-order procurement, then check the variant-name filter, variant activity, and packaging records. The 10-item search limit applies before make-to-order filtering. |
| No manufacture warehouse is available to schedule this item | Check the warehouse selection and whether an active warehouse has manufacture replenishment configured. |
| A scheduling error or a No Routing group | Read the row's Status tooltip and the summary's error message. Use the stated problem to review the combination's routing and finished-goods output-capacity setup with the person responsible for manufacturing configuration. |
| Blank or dash timing values on an error row | Resolve the message before interpreting the timing. A failed calculation is not evidence of zero production time. |
After the relevant inputs or configuration are corrected, select Create report again and check the same item, variant, packaging, quantity, status, and dates.
FAQ
Business questions
When should I use Lead Time Forecast?
Use it when you need a production-time estimate for a make-to-order finished good or want to compare returned finished-goods work-center alternatives. Set the item, package quantity, shipping reference date, and warehouse scope, then review the dates, routing, and status for the combination you need.
Why can lead-time hours differ from the time between production dates?
Lead-time hours add the required work-center minutes across scheduled routing steps. The production dates describe the earliest start and latest end on the calendar. Review the lead-time tooltip to see the step breakdown and calendar span; time between steps or shifts can make the span longer.
How should I use totals when comparing work centers?
Read them as totals of successful calculation lines in the current report. Item by Work Center can include several work-center alternatives for the same variant and packaging, so inspect those rows before using total cost or weight to prepare a production requirement.
Technical questions
What does the Quantity control represent?
It represents a package count. The report multiplies it by each packaging record's quantity and rounds the resulting item quantity to a whole number. Check the row's Quantity and unit, and use Report Parameters to confirm the packaged quantity assessed.
Why is a matching finished good missing from the forecast?
The report takes up to 10 name-matching finished goods, then retains make-to-order items. It builds lines from included variants and resolvable packaging records. Narrow Item Name, review Variant Name, and check procurement type, variant activity, and packaging before expecting a row.
Where can I find the reason a combination could not be scheduled?
Read the row's Status tooltip and Calculation Messages in the summary. The report retains calculation failures as error rows. Check the actual message before changing setup: the No Routing grouping and summary count can include errors with other causes.