Nonconformance report
A nonconformance report records a production quality issue, the investigation into its cause, and the decision about the affected material. Use it to keep the issue, responsible people, corrective work, and closure evidence together.
Open Quality Control → Nonconformance & Compliance → Nonconformance Reports, then choose View NCR details. The report number uses the NCR prefix. A report can reference a finished goods inspection, which holds the testing and quantity decision. Read the inspection and the report together when tracing the issue.
Identify the issue and who will follow it
Start with Finished Goods Inspections, Product/Process Description, Production order number, and Date of manufacture. Compare them with the production and inspection that actually produced the finding. The report's Date originated records when the issue was raised; it serves a different purpose from the manufacture date.
Keep the site roles distinct. Originating site records the site where the issue originated, while Responsible site records the site assigned to follow it. Plant, Production line, Shift, Line operator, and Shift supervisor provide the production context. Originator identifies who raised the report; Responsible manager identifies the person responsible for the issue. Naming someone in one role does not fill the others.
Read Nonconformance issue category with Description of nonconformance. The category classifies the problem; the description explains what you found. For example, Under Min Wall identifies wall thickness below the limit, while Documentation describes missing or incorrect paperwork. Use the category that fits the evidence and state the actual observation, affected material, and applicable requirement in the description.
Root Cause answers why the issue happened. It is separate from the observed defect and its category. Record the investigation's explanation and the person in Completed by. Use attachments to retain supporting evidence so the cause and proposed response can be assessed together.
Read planned work and completed work separately
The report separates what you intend to do from what you have done. This helps the responsible manager see which commitments still need attention.
| Information | How to read it |
|---|---|
| Actions to be taken | Each planned row records the action, target date, assigned person, and Completed indicator. Compare the plan with the actual work before marking it complete. |
| Implemented Actions | Each row records an action taken, its date, and who completed it. Use it to explain what was implemented. |
| QC Recommended disposition | QC's recommendation about the affected material. It is separate from the final disposition. |
| Final disposition details | The explanation and evidence supporting the final material decision. |
For example, a planned action could be to recalibrate equipment by an agreed date. The implemented-action record can describe the calibration actually performed, with its date and person. This is an illustration of the distinction; it does not make calibration the required response to a particular category.
Use CPAR Required? to record whether your issue needs follow-up through your CPAR process, and CPAR Number to retain that reference. Check the referenced work separately when reviewing completion. A flag and reference identify follow-up; they are not evidence that the work has been carried out.
Understand quantities supplied by the inspection
When you select a different finished goods inspection, the form supplies product, quantity, and available production details from that inspection. Check the populated information before relying on it: changing the inspection can replace values you entered for the previous selection.
The quantity defaults use the selected inspection as follows:
| Report value | Initial calculation or source |
|---|---|
| Total Quantity | The inspection's total quantity received. |
| Accepted quantity | Total quantity received minus inspected quantity. |
| Pipe numbers affected | The inspection's inspected quantity. |
| Scrap quantity | The inspected quantity when the inspection's failure type is Scrap; otherwise zero. |
For example, assume the selected inspection has 500 units received and 80 units inspected with failure type Scrap. The form supplies 500 total, 420 accepted, 80 affected, and 80 scrap. The arithmetic is 500 − 80 = 420. These are illustrative values, not acceptance limits or a sampling plan.
The Accepted quantity default is a subtraction, so check it against the actual material decision. It does not independently establish that the remainder passed an inspection. The displayed quantities also need the inspection's unit context; do not treat the label Pipe numbers affected as proof that a quantity was converted into a count of individual pipes.
With the same inspection selected, calculation fills empty fields while preserving populated values. Numeric zero can be treated as empty and filled again. If a zero changes, compare the current inspection and review the populated values before saving.
Use the total, accepted quantity, scrap quantity, and disposition details to account for the issue. If the quantities do not describe the material actually affected, resolve the difference with the inspection and production records. This is a review you perform; do not rely on the report to enforce an accepted-plus-scrap balance.
Interpret the final material decision
The final disposition records the chosen treatment. Read it with Final disposition details, the quantities, implemented actions, and supporting files.
| Final disposition | Meaning and evidence to retain |
|---|---|
| Accept - After Rework - Explain Below | Accepted once reworked to specification. Explain the rework and its result. |
| Accept - Offer By Concession (Attach Customer Waiver) | Accepted with a customer waiver on file. Attach the waiver supporting the concession. |
| Accept - Use As Is | Accepted without changes. Explain the basis for that decision. |
| Regrade | Downgraded to a lower grade. Record the grade decision in the details. |
| Scrap | Material is discarded and cannot be recovered. Keep the quantities and handling evidence consistent with that decision. |
| N/A - Explain Below | A disposition is not applicable; explain why. |
| Other - Explain Below | The treatment is outside the listed choices; describe it. |
Selecting a disposition records the decision. Check the finished goods inspection and related inventory movement separately to establish the material's actual stock status and location. Keep the warehouse handoff clear about what must physically happen and what has already happened.
Check whether the report is ready to close
Open is the report's initial status. Use Update as the investigation, actions, and disposition develop. Closed records that report closure has been confirmed.
Before closing, review the issue description and category, root cause, responsible people, planned and implemented actions, quantities, final disposition, attachments, and any CPAR reference. Confirm that the record supports the conclusion you are about to enter. These are review checks for the person responsible for closure, not a promise that every field or completed action is automatically validated.
Confirm issue closure is available on an Open report. The closure form records Issue closure comments, Closed by, and Date of issue closure. Confirming saves those details and changes the report to Closed. Reopen View NCR details to check the closure record and status.
Report closure and the material decision answer different questions. When handing the issue back to manufacturing or warehouse teams, check the linked inspection, inventory movement, and any CPAR work as well as the report's Closed status.
FAQ
Business questions
How does a nonconformance report differ from a finished goods inspection?
The inspection holds the testing evidence and quantity decision. The nonconformance report records the issue, its cause, responsible people, corrective work, final disposition, and closure. Use their connection to trace the issue while checking each record's own status.
Is QC Recommended disposition the final decision?
It is the recorded recommendation. Final disposition records the chosen treatment, with Final disposition details explaining it. Compare both with the quantities, actions, and supporting evidence before arranging material handling.
What should I check before closing the report?
Check that the issue, cause, actions, material disposition, quantities, supporting files, and any CPAR follow-up support your closure conclusion. Then record the closure comments, person, and date. Check the inspection and stock movement separately when confirming the material's condition and location.
Technical questions
Why did quantities change when I selected another inspection?
Changing Finished Goods Inspections replaces quantity defaults from the newly selected inspection. Total quantity comes from its received quantity; accepted quantity is received minus inspected quantity; affected quantity is inspected quantity. Scrap quantity is populated from inspected quantity only for a Scrap failure type. Verify those values against the actual disposition before saving.
What is the difference between planned and implemented action rows?
Planned rows record what should be done, its target date, assigned person, and Completed indicator. Implemented rows record the action taken, its date, and who completed it. Read both to see whether the planned response is supported by a record of the work performed.
What does CPAR Required? record?
It records whether CPAR follow-up is required for the issue, while CPAR Number records its reference. Use these fields to identify that work, then check the referenced follow-up separately; the flag is not proof of completion.