Update nonconformance report
Update a nonconformance report to connect a production defect with its investigation, planned corrections, implemented actions, and disposition. The report records what happened and what the team did; its accepted and scrap quantities are not inventory movements.
Open Quality Control → Nonconformance & Compliance → Nonconformance Reports.
Identify the affected production
Have the finished-goods inspection, affected product and quantity, originating and responsible sites, issue description, and responsible people ready. Selecting Finished Goods Inspections can fill production context and quantities. Review those values before using them: a filled accepted or scrap quantity is not an acceptance decision, and changing the selected inspection can replace related details.
Record the investigation and actions
- Find the intended report and select Update.
- On Step 1: Issue Identification, select the relevant Finished Goods Inspections. Verify the sites, manufacture date, shift, plant, production line, affected pipe numbers, product/process description, and production order reference. Record the issue category, description, originated date, originator, total quantity, recommended disposition, and responsible manager.
- On Step 2: Root Cause, record Root Cause, Completed by, and the evidence supporting the investigation. Distinguish a confirmed cause from an unresolved observation in your wording.
- On Step 3: Planned Corrective Actions, add the action, target date, assigned person, and Completed information for each planned action. Keep the plan distinct from what has actually happened.
- On Step 4: Implemented Actions, verify Accepted quantity, Scrap quantity, Final disposition, and its details. Record actual actions, dates, and the people who completed them.
- On Step 5: CPAR, record CPAR Required? and CPAR Number when applicable. CPAR refers to the corrective/preventive action request you are tracking; these fields record the requirement and reference.
- Add the relevant attachments to the investigation stages and select Update report.
Check the saved report
Reopen Update and compare the linked inspection, issue identity, responsible sites, cause, planned and actual actions, quantities, disposition, and CPAR reference. Compare the quantities with the affected goods rather than assuming the filled values are final.
Saving the report records investigation data. Use Close nonconformance report separately when the issue is ready for closure. Check the inspection and stock disposition in their own records; a report entry does not prove either work is finished.
FAQ
Business questions
When should I update an NCR?
Update the NCR as its root cause, action plan, implemented work, disposition, or CPAR reference becomes known.
How are planned actions different from implemented actions?
Planned Corrective Actions records the intended action, target date, assignee, and completion information. Implemented Actions records what was done, when, by whom, and the final disposition.
Does entering Accepted quantity or Scrap quantity move inventory?
The report stores these disposition quantities. Inspect the stock and inspection records separately to verify actual movement or an inspection decision.
Technical questions
Why should I review values after selecting an inspection?
The form can fill production context and quantities from the selected inspection. Changing the selection can replace those details, so compare them with the affected goods before saving.
Where do I record the corrective/preventive action request?
Use CPAR Required? and CPAR Number on Step 5: CPAR to record the requirement and reference. Keep the actual supporting evidence with the investigation.
How do I verify the saved investigation?
Reopen Update and compare the inspection, issue identity, sites, cause, planned/actual actions, quantities, disposition, attachments, and CPAR reference. Closing the report is a separate action.