Update the receiving and test evidence on a raw-material inspection before making its quantity decision. Saving these details is separate from registering a pass or fail.

Open Quality Control → Inspections → Raw material and select Update on the intended inspection.

Prepare the receiving and test evidence​

Match the purchase order, product, and unit of measure to the material being tested. Have the lot and rail-cart identifiers, receipt and testing dates, tester, compartment, silo, resin grade, and measured results available.

Use the Material Basics tab for Lot Number, Rail Cart Number, Date Received, Date Tested, Tested and released by, Compartment tested, Silo unloaded to, and Instructions. The tester and lot matter later: raw-material pass processing requires a valid tester and a lot number.

On Tests, select Resin type and record Date and time resin changed where relevant. Read the given and tested melt, density, and ash values as pairs. A given value records the reference you have; a tested value records the measurement. Use the approved material specification to judge the reading rather than treating a populated field as a passing result.

Save and check the evidence​

  1. Confirm that you opened the correct inspection, then enter the receiving and tester information on Material Basics.
  2. Record the resin and actual measurements on Tests.
  3. Add supporting files and Comments on Comments and Attachments so the next person can understand the findings.
  4. Select Update Inspection.
  5. Reopen Update on the same inspection. Compare the identifiers, tester, dates, resin, and paired readings with your source evidence.

Use Pass raw material inspection when the material is ready for an acceptance decision. Keep the saved measurements separate from that quantity decision.

FAQ​

Business questions​

When should I update a raw-material inspection?​

Update it when receiving identifiers, tester details, resin selection, measured results, or supporting evidence need to be recorded or corrected.

Does Update Inspection accept the material?​

The update saves the inspection data. Acceptance is a separate Inspection Passed action with its own quantity and readiness checks.

Why record both given and tested values?​

The form keeps separate reference and measured values for melt, density, and ash. Compare each pair using the material specification so another person can understand the measurement.

Technical questions​

Which information matters before a pass?​

Record the lot and a valid Tested and released by selection. If a resin is selected, check that its configured required readings are present and nonzero.

Where do I attach test evidence?​

Use Comments and Attachments for supporting files and comments. Instructions are recorded on Material Basics.

How do I verify a correction?​

Save with Update Inspection, reopen Update on the same record, and compare its identifiers, tester, dates, resin, and readings with your source evidence.