Pass finished goods inspection

Register the packaging quantity of finished goods that passed inspection. Pass processing can complete the inspection and move the accepted stock from quality control to stock. If the decision sends an Open inspection to In Review, stock movement has not been created by that attempt. Check the inspection quantities and any remainder before continuing.

Open Quality Control → Inspections → Finished Goods. Inspection Passed is offered for In Progress, Open, and Reviewed inspections.

Check the evidence and quantity​

Use Update finished goods inspection to check the resin, testers, measurements, and units. The linked control point's required readings must be present and nonzero. A resin must be selected. Use the approved specification to judge the actual readings.

Read Packaging and Total Packaging Quantity together. Inspected packaging quantity counts packages, while Total Quantity is in the item's unit of measure. The conversion uses the quantity per package. For example, if a package contains 20 m, three packages represent 60 m; those illustrative values are not defaults.

Register the passed quantity​

  1. Find the intended manufacturing order, product, and lot, then select Inspection Passed.
  2. In Register a passed inspection, compare Manufacturing order, Lot Number, Product, Packaging, and both totals with the tested goods.
  3. Enter Inspected packaging quantity as the number of packages that passed. Compare it with the current inspection's available package count.
  4. Add Inspection review instructions or Comments as appropriate, then select Register pass.

Check which result occurred​

Check the inspection status before continuing. If it is In Review, a partial attempt may already have changed the original quantities and created an Open remainder inspection. Reconcile the original and every remainder with the tested goods before any further quantity decision. Use Submit inspection review to record the assessment. Review does not itself move stock; check the quantities with the quality owner before another pass attempt.

If the original inspection is Completed, check the inspected package and unit quantities and the inventory movement from quality control to stock. A partial decision can create a new Open inspection for the remainder; compare that remainder with the quantity still requiring inspection.

If an error appears, check the inspection, any remainder inspection, and movement before repeating the action. The status and stock movement are separate effects. Correct missing actual readings or the resin selection through Update; do not substitute a guessed value to satisfy a required-field check.

FAQ​

Business questions​

When should I register a finished-goods pass?​

Use the pass decision when the tested packaging quantity has supporting measurements and is ready for acceptance. The row action is offered in In Progress, Open, and Reviewed.

Can a pass request still require review?​

Yes. Pass processing of an Open inspection can place it in In Review. A partial attempt can already have created an Open remainder, so reconcile the original and remainder quantities, record the assessment, and check the result with the quality owner before another quantity decision.

What should I hand over after a completed pass?​

Check the accepted package and unit quantities and the completed inventory movement to stock. Keep any Open remainder inspection with the quantity still requiring a decision.

Technical questions​

Do I enter packages or the item quantity?​

Enter the count shown by Inspected packaging quantity. The action converts it using the configured quantity per package; check Packaging and the unit-of-measure total together.

Why can required-reading validation reject the pass?​

The linked control point’s configured required readings must be present and nonzero, and a resin must be selected. Recheck the actual saved evidence in Update.

What should I inspect if the action reports an error?​

Check the original inspection, any Open remainder, and the associated stock movement before retrying. A changed inspection status alone does not establish that every effect completed.