Quality Control

Use Quality Control to record what was inspected, preserve the test evidence, decide the quantity outcome, and verify what happened to the material afterward. Start with the inspection stage that matches the goods: incoming raw material, work in process, or finished production.

A quality result needs more than a status label. Completed can follow a passed or failed inspection, and a recorded decision can have separate stock or production effects. Read the tested quantity, decision context, related movement, and remaining inspection work together before handing material to the next team.

Prepare the evidence for a decision​

Match the inspection to the product, lot, purchase or manufacturing order, warehouse, and unit of measure. For finished goods, also compare package count with item-unit quantity. These references prevent a correct test result from being applied to the wrong goods.

Have the actual measurements, test dates, responsible tester, applicable specification, and supporting files ready. Control points describe the intended checks; a resin specification can identify required readings and carbon-black limits. A present or nonzero reading is a completeness check, not a universal acceptance rule.

Before a stock-related decision, check the warehouse locations needed for that path. Afterward, inspect the movement and any follow-up production work as well as the inspection's state. Resolve a reported error against the records already created or changed before repeating the action.

Start with the work in front of you​

Your situationStart withResult to check
An incoming delivery needs test evidence and a quantity decisionRaw-material inspectionsReceiving identity, actual readings, decided quantity, movement, and any Open remainder.
A production-stage check needs context or review evidenceIn-process inspectionsProduction identity, control point, review evidence, and the inspection's own outcome.
Finished production needs assessment and a quantity decisionFinished-goods inspectionsMeasurements, any review, package and unit quantities, stock destination, and follow-up work.
A defect needs investigation and corrective-action trackingNonconformance reportsResponsibility, cause, planned and implemented actions, disposition, and closure evidence.
You need conformance evidence for produced goodsCertificates of ConformanceCustomer/production match, certificate state, and signing details actually displayed.
The inspection definition needs a changeRaw-material, in-process, or finished-goods control pointsSaved scope, method, frequency, test selections where provided, and configuration status.
A resin grade's reading requirements or carbon-black range needs maintenanceResin SpecificationsThe intended grade, selected readings, and percentage limits.
A procedure needs authoring or readingCMS for authoring; Training Manuals for readingSaved content and revision details, then publication availability.

Keep each record's job clear​

An inspection records one case: the goods, readings, review context, quantity decision, and result. A control point is a reusable definition of the checks. Changing a definition does not itself record a test result on an inspection.

A nonconformance report, or NCR, carries the issue investigation and corrective work. Its accepted and scrap quantities describe disposition information; check the actual stock handling separately. A certificate of conformance records a statement about produced goods and specifications. Read its signing evidence with the production/customer references.

A CMS article holds a procedure or reference. Its published state controls its availability in Training Manuals; reading an article does not record an inspection decision.

Work through a partial inspection​

Suppose an incoming inspection covers 100 kg and the evidence supports accepting 60 kg. The pass action processes those 60 kg and leaves a new Open inspection for the remaining 40 kg. Check the accepted quantity's stock movement before handing it to production, and keep the 40 kg remainder visible as unfinished inspection work.

For a finished-goods failure, disposition also matters. Rework and Scrap have different stock destinations and follow-up production records. Check the finished-goods decision guide before submitting rather than treating a failure label as completed physical handling.

Continue with connected work​

For incoming material, the Purchasing process explains receiving and billing alongside the inspection branch. Keep the goods receipt and purchase order available when reconciling a partial inspection with the full delivery.

For the production work around these checks, use Plan to produce and release for the planning, operation, and production-reporting context. Carry the manufacturing order, lot, inspected quantities, movement, and any remainder or follow-up order to the next team. Check those records individually; menu order does not establish a mandatory sequence of review, certificate issuance, and stock release.

FAQ​

Business questions​

Which inspection should I start with?​

Choose raw material for incoming material, in-process for a production-stage check, or finished goods for completed production. Match the order, product, lot, warehouse, and quantity to the goods being checked.

Does Completed mean the goods passed?​

No. Passed and failed quantities can both complete an inspection. Check the decision context, quantity, related stock movement, and any remaining inspection work.

When do I need an NCR rather than only an inspection?​

Use an NCR when the issue needs responsibility, root cause, planned and implemented corrective actions, disposition, and closure tracking in addition to the inspection record.

Technical questions​

How do I distinguish packages from item quantity?​

Finished-goods decisions use a package count and convert it using the configured quantity per package. Read the packaging and unit-of-measure totals together before submitting.

What should I check after a partial decision?​

Check the original decided quantity, any Open remainder inspection, and the related movement. Keep the remainder separate from material already decided.

Why might a procedure be absent from Training Manuals?​

Training Manuals lists Published CMS articles. Check the article name and publication status with the person maintaining it; Draft or unpublished content is not in that reading list.