Blanket purchase order

A blanket purchase order records an agreement with a vendor for specified products, quantities, prices, and dates. Use it when purchases draw on that agreement over time. The agreement holds the planned quantity; a purchase order records a particular purchase against it.

A release is the quantity recorded as used against the agreement. Releasing quantity and receiving goods are separate events. Read the agreement's released, open, and fulfilled quantities together before deciding how much remains available or how much has arrived.

Read the agreement and its lines together​

Start with the blanket purchase order number, vendor, currency, start date, and end date. These identify the agreement you intend to use. Compare the vendor and currency with the purchase order before relying on an agreement price.

Payment terms describe the agreement's payment conditions. Calculation fills empty terms from the vendor's net terms; terms already recorded on the agreement remain in place. Notes and attachments keep supporting information with the agreement.

Each agreement line identifies a product, variant, packaging, internal unit, vendor item, quantity, and price. Keep the vendor and internal units distinct when reviewing quantities. When they represent the same unit, calculation uses vendor quantity as the internal quantity. The vendor item also contributes its unit, package size, and lead time.

Calculation reports a vendor quantity below the price-list minimum or one that is not an exact multiple of the vendor package size. Review these messages before saving a changed agreement. For example, a vendor package size of 10 allows a vendor quantity of 30; 35 produces a package-multiple error. These numbers illustrate the rule, not a default package size.

Keep one agreement line for each product, variant, unit, and packaging combination. Duplicate matching lines can make a release ambiguous and cause it to fail.

Check when the agreement can support a release​

The agreement must be Active, and its start and end dates must cover the purchase order's order date, for release processing to use it. A price displayed on an order is not enough to establish that the agreement is ready for release.

The states distinguish approval, availability, and closure:

StateHow to interpret it
Pending ApprovalThe default state for a new agreement. Approval changes it to Active.
ActiveThe agreement is available for release, subject to its dates and matching quantities.
On HoldThe agreement is suspended. Release processing accepts Active agreements. Reactivation changes On Hold back to Active.
FulfilledCalculation found no quantity left to receive on any agreement line, with some quantity recorded as received.
Cancelled or ExpiredThese states do not qualify for a new release.

The record also supports Draft. Do not treat a saved agreement as available until it is Active and its dates are suitable.

An end date before the start date produces a calculation error. Expiry processing can change an Active agreement to Expired after its end date. Check both dates and status when reviewing an older agreement; the date check still matters while a record shows Active.

Line planned receipt dates are separate from the agreement's validity period. A calculated line date starts from the agreement start date plus the line's lead time. Check that date against the vendor's delivery plan rather than treating the agreement end date as the expected arrival date.

Understand how a purchase order uses the agreement​

Selecting a blanket purchase order on a purchase order lets its calculation look for an agreement price. A covering line must match the product, variant, packaging, and unit, and have enough quantity remaining to cover the whole purchase-order line. If several lines can cover the quantity, calculation chooses the lowest price. Resolve duplicate agreement lines before attempting a release.

If no line can cover the quantity, the order's system price returns to its vendor price list. Read the order's pricing message and compare it with the vendor agreement before confirming.

Purchase-order confirmation calls release processing for the selected agreement. A successful release adds entries for the matching quantities and recalculates the agreement. Check the released and open quantities after confirmation to verify the expected change.

There are two important exceptions:

  • A purchase-order line that is not on the agreement is left off the release.
  • A line requesting more than the remaining agreement quantity is also left off the release. It is not split automatically into an agreement portion and an excess portion.

For example, if a matching agreement line has 60 units left to release, a 70-unit order line is not recorded as a 60-unit release. Review the purchase order's quantity and price source before proceeding.

Distinguish planned, released, and received quantities​

These values describe different work. Open quantity measures agreement capacity remaining to release; quantity left to receive measures goods still outstanding against the agreement's recorded line quantity.

ValueCalculation or meaning
Planned total quantitySum of agreement line quantities.
Released total quantitySum of recorded release quantities matching the agreement's lines.
Open quantityPlanned quantity minus released quantity.
Fulfilled total quantitySum of quantities recorded as received on the agreement lines.
Quantity left to receiveAgreement line quantity minus its recorded received quantity.
Order completion percentageReleased quantity ÷ planned quantity × 100; zero when planned quantity is zero.

Suppose one agreement line plans 100 units at $5 each. It has recorded releases totaling 40 units and a received quantity of 25 units. The resulting comparisons are:

CheckResult
Still open to release100 − 40 = 60 units
Still to receive against the agreement line100 − 25 = 75 units
Order completion40 ÷ 100 × 100 = 40%
Planned value100 × $5 = $500
Released value at the current agreement price40 × $5 = $200
Fulfilled value at the current agreement price25 × $5 = $125

The example assumes one unit of measure and no price changes. A 100% order-completion value means the planned quantity has been released; it does not by itself show that everything has arrived.

The details section labeled Items received across purchase orders lists release entries. An entry is created when quantity is released, so its presence alone is not proof of physical receipt. Check the linked purchase orders' receipt and billing progress when tracing delivery or billing.

Compare agreement values with the summary total​

Planned value is quantity multiplied by the current agreement line price. Released and fulfilled values use their respective quantities at the current agreement price. They exclude shipping and tax, and they are not a historical total of posted vendor bills.

The summary total uses the agreement line amounts, shipping, and tax. A line amount before tax is price multiplied by quantity, plus its shipping cost. A taxable line with a positive rate adds tax on that amount; an untaxed line keeps the amount including shipping.

Using the example's planned value of $500, an illustrative $10 shipping charge and 10% tax give an amount before tax of $510, tax of $51, and a summary total of $561. Planned value remains $500 because its calculation excludes those charges.

Tax calculation uses the vendor's shipping address, or its first address when no shipping address is identified, and the agreement start date. Read the line tax message and check a custom rate before comparing the agreement summary with a purchase order or vendor document.

Review changes after releases exist​

You cannot reduce a matching agreement line below the quantity already released. Calculation restores the released quantity and produces an error, which stops the save. Review the released balance before changing the agreed quantity.

An agreement update recalculates that record. It does not reconcile or rewrite the purchase orders and receipts already connected to it. Compare those records separately when correcting a price, quantity, or delivery difference.

FAQ​

Business questions​

How does a blanket purchase order differ from a purchase order?​

The blanket purchase order records the vendor agreement and its planned quantities and prices over a date range. A purchase order records a particular purchase. When its matching quantity is successfully released, that quantity is recorded against the agreement.

Does 100% order completion mean all materials have arrived?​

No. The percentage uses released quantity divided by planned quantity. Read fulfilled quantities and the purchase orders' receipt progress to check arrival. Releasing all the planned quantity can happen before receiving it all.

What happens if an order line exceeds the agreement's remaining quantity?​

That line is left off the agreement release. It is not partly consumed up to the remaining balance. Review the order quantity and pricing message; when no agreement line covers the whole quantity, calculation uses the vendor price-list price for a system-priced line.

Technical questions​

Which status and dates allow a release?​

Release processing requires an Active agreement whose start and end dates cover the purchase order's order date. Check the agreement's dates and the recorded release result, even if an agreement price is already displayed on the order.

Why will a reduction below released quantity not save?​

The line cannot be smaller than the quantity already released against the same product, variant, unit, and packaging. Calculation restores that released quantity and reports an error. Compare your intended change with existing releases before retrying.

Why can planned value differ from the summary total?​

Planned value is quantity multiplied by agreement price and excludes shipping and tax. The summary total includes line shipping and any calculated tax. Compare the same components and currency when reviewing the difference.