Plan to produce and release
Use this process when a production requirement is ready to become manufacturing work. It connects the material and operation plan, work orders, reported production, quality decisions and finished stock.
Follow quantities as well as statuses. A completed manufacturing order records the production result; goods routed to quality assurance still need their inspection decision and movement to stock. A certificate of conformance is a separate record to check when the product requires one.
The quality path depends on active control points for the manufactured item. In-process checks, inspection review, scrap and certificates have their own checkpoints below.
Check the plan and supporting setup
Start with the item, variant, quantity, unit of measure and packaging. Check the warehouse and production dates against the requirement being fulfilled. A package count and an item quantity can describe different amounts, so establish their conversion before scheduling or reporting.
Prepare the following information before the relevant stage:
| Work | Readiness check |
|---|---|
| Material and operation plan | An applicable BOM and routing exist for the item and variant. The BOM describes materials; the routing supplies operations and their requirements. |
| Scheduling | Routing operations can be placed on active work centers with valid start and end dates. Check the work instructions and dependencies that apply. |
| Production reporting | The manufacturing order is In Progress with quantity remaining. Material lots, quantities, recorded time, scrap and downtime details describe the work actually performed. |
| Stock posting | The warehouse has stock, production and quality assurance locations configured. Scrap hold and rework destinations must support any disposition you use. |
| Inspection | Applicable control points, product and resin specifications, required measurements and packaging are ready for the quality decision. |
A missing reference or material shortage needs correction at its source. Do not change reported output, time or measurements merely to get past a validation message.
Turn the production plan into operation work
Create and review the manufacturing order with its product, quantity, BOM and routing. Read the material plan and the operation plan together: a valid product reference alone does not establish that the manufacturing work is ready.
Confirmation schedules the routing operations and creates their work orders. Check the resulting work centers, dates and dependencies before handing work to the floor. Where the plan includes subassembly orders, confirmation is managed through the parent production structure; do not confirm a subassembly independently.
Use Shopfloor work orders to find the assigned operation and read its job sheet. Keep the manufacturing order and work order numbers together so instructions, quantities and time refer to the same work.
Execute and close the operation
Check saved input consumption, raw materials and output quantities against the operation performed. Work-order completion can process material consumption according to Manufacturing settings and can create in-process inspections when work instructions match active control points.
Predecessor rules matter. An operation can require earlier work orders to be Completed, and inputs supplied exclusively by a preceding operation need enough recorded upstream output. A completed predecessor status alone does not establish that its output quantity is sufficient.
Use Complete work order for the quantity review, material effects and blocked-operation checks. Completion of one operation does not establish that the manufacturing order's required finished quantity has been produced. Track any resulting in-process inspection with the quality work for that order.
Post the production report and follow the output
The production report brings together output, material lots, scrap, productive time and downtime. Review these before confirming the production report.
The finished quantity credited to the order must be an exact multiple of the configured quantity per package. Resolve a package mismatch before posting, including when only the remaining order balance will be credited.
Confirmation completes the report and creates time tickets for its productive time and downtime. Where reported materials are present, it processes their consumption from stock to production and moves reported waste from stock to scrap hold. Material processing and validation depend on the order's consumption approach and Manufacturing settings; use the production report explanation to interpret those quantities.
Reported output is recorded against the manufacturing order. Reconciliation updates completed and remaining quantities; reaching the assigned quantity can complete outstanding work orders and the manufacturing order. Overproduction is recorded separately, and the quantity credited by that report is capped at the remaining order balance.
Check the finished-output movement's destination next:
- When active finished-goods control points apply to the item, inspections are created and the output is directed from production to quality assurance.
- When none applies, the output movement goes from production to warehouse stock.
Check the completed report, updated manufacturing-order quantities and completed movements together. A report status alone does not establish the output's destination or quality outcome.
Decide the inspected quantity and release it
For goods in quality assurance, use the finished goods inspection to match the manufacturing order, lot, product, warehouse and test results. Record the actual required readings and resin information before a decision.
A pass attempt on an Open inspection can require review when the configured ovality, wall-thickness or carbon-black limits are exceeded. Submitting inspection review records the assessment and changes the state to Reviewed. It does not move stock; the quantity still needs a pass or fail decision.
A partial pass attempt can already have reduced the original inspection's quantity and created an Open remainder before the original enters review. Reconcile both records with the tested goods before making another quantity decision.
A successful finished-goods pass creates and completes the movement from quality assurance to warehouse stock. Read inspected package count with the quantity in each package. The decision converts packages to the item's unit quantity, and a partial decision creates a new Open inspection for the remainder.
Check the passed quantity and the completed movement before handing that quantity to the warehouse. A Completed inspection can also describe a failed decision, so read its outcome and destination rather than treating Completed as a pass.
Follow rework and scrap to their own result
Use the disposition established for the failed goods when recording an inspection failure.
| Path | What follows | What to verify |
|---|---|---|
| Rework | Failed goods move from quality assurance to rework, and a rework order records the required work. Rework completion returns the processed quantity to quality assurance and creates another inspection. | Rework instruction, quantity, completed movement and new inspection. Reworked goods still need a quality decision before release to stock. |
| Scrap | Failed goods move to scrap hold and a Draft replacement manufacturing order is created for the failed quantity. | Failed quantity, scrap-hold movement and replacement order. Scrap hold does not establish physical disposal or completed replacement production. |
| Partial decision | An Open inspection carries the quantity still needing a decision. Partial rework can also leave a separate rework order for its remaining quantity. | Match the processed amount and remainder with the original quantity; follow each record separately. |
When scrap is intended for material recovery, Scrap Regrind is a separate conversion. It consumes stock from scrap hold into scrap and receives recovered raw material from scrap into stock. Review the weight, output definition and resulting movements; the failed inspection itself does not perform that recovery.
Keep the investigation with the affected inspection
When a production quality issue needs investigation, use the Nonconformance report to keep the issue, root cause, responsible people, planned and implemented actions, and disposition details together. Match its selected finished-goods inspection with the affected product and production before handing the issue to the next person.
Selecting another inspection can replace the report's populated product, quantities, and production context. Check those values before relying on them. In particular, its Accepted quantity initially subtracts inspected quantity from total quantity received; that subtraction does not establish that the remainder passed inspection.
Read the investigation and actual material handling together. Use the finished-goods inspection's decision and completed movement to establish the goods' location and released quantity. A recommendation, final-disposition label, or investigation record alone does not substitute for those stock checks.
Check the certificate after release
After the finished-goods pass movement, automatic certificate creation checks whether the manufacturing order already has a certificate and whether the item requires generation. A matching specification template is also needed. Certificate presence is therefore conditional.
Use Certificate of conformance to review the product, production and customer context and the approval evidence. Generation and signature are separate checks. Do not use a certificate's presence or signature as a substitute for verifying the quality-to-stock movement; that movement is the release checkpoint in this process.
Reconcile progress before the handoff
Use these checkpoints to locate unfinished work:
| What you have | Check before continuing |
|---|---|
| Scheduled work orders | Centers, dates, dependencies, instructions and material supply describe the intended operation. |
| Completed production report | Saved output, time tickets, consumption/scrap movements and the manufacturing order's updated balance agree with the run. |
| Completed manufacturing order | Review the final quantities and finished-output destination. Goods can still be in quality assurance. |
| Reviewed inspection | Read the assessment and proceed to the supported quantity decision; review alone has not released stock. |
| Completed inspection | Check pass/fail outcome, inspected quantity, movement destination and any Open remainder. |
| Finished stock | Match quantity, item, lot, warehouse and completed movement to the production being handed over. Check the certificate separately where required. |
If posting reports an error, inspect the current report, order, inspection and related movements before another attempt. Give the responsible production, inventory or quality person the same record numbers and the returned message. Do not repeat a posting based only on an unchanged screen.
Example: production finished, inspection partly released
Assume an order is for 100 units, packaged as 10 units per package, with one active finished-goods control point. There are no transfers or overproduction, and the production report's materials, time and validations are ready.
A completed report for 10 packages × 10 units = 100 units fulfills the production quantity and routes the output to quality assurance. The manufacturing order can be Completed at this point.
If the inspection passes 6 packages, the release covers 6 × 10 = 60 units. A new Open inspection carries 4 packages, or 40 units. Hand off 60 units as released, with the remaining 40 still requiring its inspection decision. Check any required certificate separately from that quantity reconciliation. These values illustrate the process; they are not defaults.
FAQ
Business questions
Does a Completed manufacturing order mean all goods are released?
No. It records production completion. When finished output was directed to quality assurance, check the inspection decision and completed quality-to-stock movement for the quantity being handed over.
Does every production report create a finished-goods inspection?
The finished-output stage checks for active finished-goods control points for the manufactured item. Matching points create inspections and direct the output to quality assurance; without them, the output movement goes to stock. Check the resulting records and destination for the batch.
Are reworked goods released as soon as rework is completed?
No. Rework completion returns the processed goods to quality assurance and creates an inspection. A further quality decision and release movement are needed before treating that quantity as released stock.
Technical questions
When do production time and material postings occur?
Production-report confirmation completes the report, creates the productive-time and downtime tickets, and processes its applicable reported consumption and scrap movements. Work-order material consumption also follows Manufacturing settings, so reconcile the report and operation records together.
What happens when only part of an inspection passes?
The passed package count is converted to item units and released through its movement. A new Open inspection carries the remaining quantity. Compare both records with the original total instead of treating the entire lot as released.
Why might no new certificate appear after a pass?
Automatic generation follows the release movement and depends on the item's certificate policy and a matching template. An existing linked certificate prevents another one being created. Check the manufacturing order and certificate context; certificate generation is separate from the stock-release result.