Work order

A production work order instructs one operation under a manufacturing order and assigns it to a work center. Use it to compare the operation's material requirements, schedule, recorded work, and cost. Maintenance work orders record a dated interruption at a center.

Open Manufacturing → Operations → Work Orders, then choose Details for the record. Work order numbers use the WO prefix. Job Sheet presents the production and instruction context for the floor; Details also includes planned and actual costs and time reports.

Identify the operation and its parent order​

Read the work order number with Manufacturing order, product, variant, quantity, and Work Center. These identify the operation you are reviewing. The manufacturing order describes the overall production commitment; this record describes the operation contributing to it.

The original routing node connects the operation to its routing definition. Work Instructions identifies the procedures assigned to the operation, with their per-unit and total duration. Read the linked work instruction for the directions and supporting files when checking how the work should be performed.

The warehouse identifies the inventory context for the work order. Raw material lines add their location and, when recorded, identified stock. Match those details as well as the item when tracing material consumption.

Interpret status, type, and dependencies​

Read Status with the quantities and time reports. A status describes the operation's state; the line quantities explain the recorded work.

StatusMeaning
DraftA created work-order record.
OpenThe work order is open, with no time logged.
In ProgressTime has been logged and the work order is unfinished.
SchedulingThe work order is being scheduled.
CompletedThe work order has been completed. Check its quantities when interpreting the result.
MaintenanceA maintenance work order.

Type distinguishes Production, Maintenance, Downtime, and Subcontract work. A maintenance entry created through Log downtime reserves a dated period at the center, with a reason and description. It represents a different kind of work from a production operation with input and output parts.

Under Key statuses, Work start rule tells you whether work may start before the preceding work order is completed. With Do not allow start until previous work order is completed, check the dependent work orders before completing this operation: unfinished predecessors prevent completion.

For input parts sourced only from the previous step, completion also checks that upstream output covers the required input quantity. A routing that permits stock sourcing has a different material supply check. Read the part source and dependency context together when investigating a blocked operation.

Compare the schedule with recorded time​

Read current Start date and End date beside Planned start date and Planned end date. The current dates identify the scheduled interval; the planned dates provide the plan for comparison. The scheduling fields include date and time in UTC.

Keep the scheduled interval separate from Actual minutes. Actual minutes is the sum of the durations on associated time tickets for this manufacturing order and work order. Two people recording 30 minutes each contribute 60 recorded minutes, even if they worked during the same half-hour.

In Time reports for work order, inspect the employee, Clock in time, and Clock out time when a recorded duration needs explanation. Production reports provide output and shift context. Use the report's shift reference when tracing which work shift the production belongs to.

The operation calculation derives production duration from Duration per unit (min) multiplied by the manufacturing-order quantity, then adds Setup time (min) and Cleanup time (min) for its planned total. Setup and cleanup come from the selected work center. After a scheduling change, compare the saved Total time (min) with the saved start and end again: a date update records the revised interval and can adjust dependent work orders.

Work-instruction durations provide another useful check. Each instruction's total minutes is its duration per unit multiplied by the manufacturing quantity. Read the instruction totals alongside the operation's duration when investigating an estimate.

Read input, output, and material quantities together​

The three line groups describe different parts of the operation:

GroupWhat it contributes
Input partsParts expected to be consumed by this routing step, including parts supplied by earlier operations.
Output partsParts produced by this step for use by later operations.
Raw materialMaterial required for this work, with item, variant, unit, and inventory context.

For each line, compare Quantity Per Unit with Total Quantity Required. The operation calculation multiplies the per-unit quantity by the manufacturing-order quantity. Match the unit of measure and packaging before comparing values between lines.

For example, 10 finished units requiring two component units each give a total requirement of 20 component units. If 12 have been consumed, the remaining requirement is eight. This is a requirement calculation; check the inventory context separately when deciding whether stock is available.

Keep Quantity consumed, Quantity Produced, and Quantity Available distinct. Consumed describes usage. Produced describes output made by the operation. Available describes output available to later steps. Read the requirement and remaining balance with the corresponding quantity, rather than treating every quantity as finished output.

An input part can also record the portion consumed from stock. Consumption logs connect actual stock consumption to inventory movements, with a consumption date and a reversal reference when applicable. Use those records when tracing a stock movement behind a quantity; a required quantity alone does not establish that stock has moved.

Explain a cost difference​

The Planned vs Actual section compares total, labor, and raw material costs. Start with the labor and material comparisons to locate the difference, then check the total in the same currency.

CostHow the operation calculation derives it
Planned cost per hourThe selected work center's hourly rate.
Planned cost per minuteHourly rate divided by 60, rounded to two decimal places.
Planned labor costPlanned cost per minute multiplied by planned total minutes.
Planned raw material costSum of required raw material quantities multiplied by their recorded unit costs.
Planned total costPlanned labor cost plus planned raw material cost.
Actual labor costSum of the associated time tickets' recorded total costs.
Actual raw material costSum of consumed raw material quantities multiplied by their recorded unit costs.
Actual total costActual labor cost plus actual raw material cost.

For an illustrative plan of 10 units at three minutes per unit, five setup minutes, and five cleanup minutes, planned time is 40 minutes. At 60 per hour, the per-minute rate is one and planned labor is 40. A raw material requirement of 20 units at two per unit adds 40, giving planned total cost of 80.

If the saved time tickets total 45 minutes and 54 in cost, and recorded material consumption is 18 units at two per unit, actual material cost is 36 and actual total cost is 90. These example amounts use one currency. Check ticket costs and consumed material when explaining the difference; the scheduled interval alone cannot explain the labor total.

Check the record before completing or changing it​

Before completing an operation, compare its input and raw material consumption with requirements, and its output produced with the expected output. Check the assigned center and any upstream dependencies as well.

Completion fills a zero consumed quantity to the total required quantity for input and raw material lines. It also fills missing output production and availability from the required output quantity. A nonzero recorded consumed quantity is retained. Review the quantities before completing so these rules do not substitute a planned amount for an unrecorded result you still need to investigate.

Material consumption timing follows Manufacturing settings. It can occur at work-order completion or be deferred to manufacturing-order completion. When consumption occurs for the operation, stock movements and consumption logs provide the trace. Work instructions matched to active in-process inspection control points can also lead to in-process inspection records during completion.

Completing a production work order marks that operation Completed and can advance its Open manufacturing order to In Progress. Check the parent order's quantities and status separately when deciding whether the overall production commitment is finished.

Use Update to change the operation's center, dates, part requirements, materials, or instructions while it is Draft or Open. The update task explains a center/date change and the saved schedule checks. A schedule change can move other Draft or Open work orders in the same manufacturing order. Recheck the affected schedule after saving. Use Details for the cost and time review and Job Sheet for the floor's production context.

Complete a work order explains the saved-quantity review, material and quality effects, and recovery from a blocked completion.

FAQ​

Business questions​

How does a work order differ from a manufacturing order?​

A manufacturing order describes the overall production commitment. A production work order instructs one operation under that order and assigns it to a work center. Use the work order to investigate that operation's materials, time, and costs.

Why can actual cost differ from the plan?​

Planned labor uses the work-center rate and planned minutes, while actual labor uses recorded time-ticket costs. Planned materials use required quantities, while actual materials use consumed quantities and recorded unit costs. Compare labor and material separately to find what changed.

Does Completed mean the entire manufacturing order is finished?​

No. It identifies completion of this work order. Completing the operation can advance an Open manufacturing order to In Progress. Check the parent order's own quantities and status for the overall result.

Technical questions​

Where do Actual minutes and Actual labor cost come from?​

The operation calculation totals the associated time tickets: their durations contribute Actual minutes and their recorded costs contribute Actual labor cost. Inspect the employee and clock-in and clock-out times in Time reports for work order when the total needs explanation.

How is a line's total required quantity calculated?​

It is the per-unit quantity multiplied by the manufacturing-order quantity. For example, two component units per finished unit for an order of 10 require 20 component units. Read that total with its unit of measure, then compare it with consumed or produced quantity as appropriate.

Why can an upstream work order prevent completion?​

With Do not allow start until previous work order is completed, unfinished dependent predecessors prevent completion. When input parts are sourced only from the preceding step, their upstream produced quantities must also cover the requirement. Check both dependency status and the part source when investigating the block.