Update work order
Update a work order’s assigned work center or planned dates when its operation needs a different slot. Saving can also change related work orders’ dates, so check the wider plan afterward.
Open Manufacturing → Operations → Work Orders. Update is shown for Draft and Open work orders.
Prepare the change
Use Details to verify the work-order number, parent manufacturing order, current work center, dates and predecessor operations. Have the intended center and start/end times ready. The center selector is constrained by the work order’s warehouse context.
For an operation that must wait for its predecessor, the proposed start must not be earlier than the relevant predecessor’s end. A permitted early-start rule does not remove the need to check material readiness.
Save the resource or date change
- Choose Update on the intended work order.
- Select Work Center for the resource that should perform the operation. Review Start date and end at as a pair; the latter is the planned end date and time.
- Check the operation’s input/output parts, raw materials and work instructions against the intended work. This procedure covers the center and date change.
- Choose Update Work Order.
Keeping the center and changing dates can reflow dependent Draft/Open work orders in the same manufacturing order. A center change can also close a gap on the old center and place the moved order after work on the new center. The saved dates may therefore differ from the dates you entered.
Verify the plan
Reopen Details and compare the saved center, start, end and Planned Time. Then inspect the Production Schedule and related work orders, including the old and new centers when moving a job.
For example, moving an operation out of a 10:00–11:00 slot can alter the following operation’s slot. Verify its actual saved times before communicating the plan.
If the start is rejected for preceding a parent operation’s end, review the predecessor dates and choose an appropriate start. If a manufacturing order or work center cannot be found, correct that reference before retrying. After an interrupted save, inspect the saved work order and related dates before submitting again.
Read the work-order record for planned requirements, time and cost meanings.
FAQ
Business questions
When should I use this task?
Use it when a Draft or Open operation needs a different work center or planned dates. Confirm the operation and parent manufacturing order before changing the slot.
Why review other operations after saving?
The update can reflow related Draft/Open work orders in the same manufacturing order, including dependent operations and work on the affected centers.
What should I check when choosing another center?
Check the intended production resource and the warehouse context. The selector uses the work order’s warehouse to constrain the center search.
Technical questions
Why can a proposed start be rejected?
For an operation that cannot start before its predecessor, a start earlier than the relevant predecessor’s end is rejected. Review the predecessor and select an appropriate start.
Will the saved dates always match my entries?
No. A center change can place the moved order after work at the new center and alter related dates. Reopen Details and compare the saved start and end.
Where do I verify the result?
Check Details for the saved center, dates and Planned Time, then inspect Production Schedule and the related operations at the affected centers.