Work Orders

Work Orders tracks the operations assigned to production resources. Use it to check an operation’s plan, review its actual time and cost, adjust a Draft/Open slot, and complete work after checking its saved requirements.

Open Manufacturing → Operations → Work Orders.

Establish the operation’s context​

Identify the Work order, Product, Manufacturing order, Work Center, and Type together. Several operations may serve the same manufacturing order; the parent number alone does not identify the operation.

Read Start date, End date and Planned Time beside Status. Compare Planned cost with Actual cost in the same currency. These comparisons help decide whether the next action is a planning change, investigation of reported time/cost, or completion.

Use Details for operation information. Job Sheet is another operation view for the job context. The work-order record explains its material, instruction, time and cost groups.

Choose the supported next step​

SituationPath and checkpoint
A Draft/Open operation needs a different resource or time slotUpdate work order; verify its saved dates and the related plan.
Output needs reportingCreate production report; check the selected manufacturing order, operation, center and shift.
An operation is ready to closeComplete work order; review saved consumption, output and instruction durations first.
Several operations need reviewing by resource and dateOpen Production Schedule.

Update is shown for Draft/Open. complete is shown for Draft/Open/In Progress, but the completion checks still apply. An available action does not establish that materials or predecessors are ready.

Check completion before handing off​

Completion checks the saved work order and its dependencies. It can fill empty or zero consumption, output and instruction-time values from planned requirements while retaining positive recorded amounts. Check these values before committing; the completion task explains the limits of editing its panel.

After completion, confirm Completed and compare the saved quantities and time. Review the parent manufacturing order separately for overall progress; closing an operation and finishing all manufacturing demand are different checkpoints.

If completion reports missing input supply or an unfinished predecessor, inspect those referenced operations and quantities before retrying. For unexpected cost differences, compare the time tickets and center rates with the operation’s actual values.

FAQ​

Business questions​

How do I distinguish an operation from its overall production demand?​

The work order identifies an operation and assigned resource. The Manufacturing order column identifies the parent production demand; several operations may serve it.

When should I use the schedule instead of this list?​

Use Production Schedule to compare operations by resource and date. Use Work Orders to inspect a specific operation’s status, time, cost and available actions.

What should I review before closing an operation?​

Review saved material consumption, output, instruction durations, predecessor readiness and input supply. Completion can fill empty or zero actual values from the plan.

Technical questions​

When is Update available?​

The Work Orders list shows Update for Draft and Open records. Verify the saved dates and related plan after updating.

Does a visible complete action prove readiness?​

No. It is shown for Draft, Open and In Progress, while completion still checks dependencies and material supply. Follow the completion task’s checks.

How should I investigate planned versus actual cost?​

Compare the values in the same currency, then inspect the work order’s actual time and costs, linked time tickets and relevant work-center rates.