Create production report by quantity

Use Create PR by quantity in Production Schedule when the manufacturing order already uses quantity-based material consumption. Package count determines the report's output quantity, and the order's per-unit material requirements determine consumption for matching BOM materials. You still record the time spent on the run.

Check the consumption method first​

This form has no Actual Weight input. Use it for an order configured to calculate material consumption by quantity. Opening the form does not change the manufacturing order's consumption method. Verify the method with the person responsible for the order before entering the run.

For weight-based consumption, use Create production report, which includes Actual Weight. Weight-based calculation needs that input; the quantity form does not provide it.

Have the work order, reporting date and time, shift, package count, productive hours, material lots, and any downtime details available. The work order needs an active work center and a valid manufacturing order, product, variant, packaging, units, and warehouse.

Creating the report saves a Draft for review. Confirmation is the separate task that completes production and posts time, inventory, and manufacturing-order activity.

Enter the work and output quantity​

  1. Open Manufacturing → Operations → Production Schedule and choose Create PR by quantity. The form is titled Create production report.

  2. Select Work order. Check the displayed Manufacturing order, Product, Work Center, warehouse, and Unit of Measure against the run. Correct the work order selection before entering results if this context describes different work.

  3. Enter Manufacturing Date, including the date and time for the run being reported. On later confirmation, the report date supplies the starting point for the generated productive-time and downtime tickets.

  4. In Production Report, select Shift and enter Packaged quantity. Read Packaging, calculated Quantity, and Unit of Measure together. The Quantity in this section is the report's output; the Quantity beside the work-order details provides manufacturing-order context.

    For example, with 20 units per package, 10 packages give 200 units of reported output. Use the actual selected package definition; these numbers are illustrative.

Check material quantities and recorded time​

  1. In Raw Materials, select Stock/Lot for the material used. Check the displayed Lot Number and Unit of Measure. Use Add raw material when another consumed lot needs a line.

  2. Review each material Quantity after calculation. For a material that matches the order's BOM, quantity-based calculation uses its per-unit requirement multiplied by this report's output. Entering another amount in the Quantity field does not by itself establish an override: the calculation can replace it with the BOM-derived amount.

    A material outside the order's BOM retains its entered quantity. Check that amount against actual use and the selected lot's stock. Resolve a difference between the BOM-derived amount and actual consumption with the person responsible for the order before saving a report that would misstate the run.

    Percentage Mix is visible, but the quantity-based order uses its per-unit requirements rather than the weight-based percentage calculation. Do not use a different percentage to force a BOM material quantity to the amount you want.

  3. In Time spent, enter Up Hours for productive time. Quantity does not calculate this time for you. Enter hours, rather than minutes, and check that the value is greater than zero.

  4. For interruptions, use Log downtime in Downtime. Enter Down reason, Hours, and Downtime description. Use Log additional downtime for another event. The report sums these line hours into Down Hours. Check productive time plus downtime against the run record and the configured reporting-hours limit or exact-total rule.

    For example, 200 units produced in seven productive hours and one downtime hour still require those hours to be entered. The report's average quantity output rate is based on eight total hours. See Production report for the rate and cost calculations.

Review and save the draft​

  1. Add Description of work, Comments, and supporting files in attachments where they help explain the run. Review any loss information before proceeding. Quantity-based calculation clears the weight-based scrap totals, so a zero total scrap weight is not evidence that the run had no loss. Reconcile scrap details with the responsible person before confirmation.

  2. Compare the report's calculated output and material quantities with the package count, BOM requirements, lots, and actual run record. Check the material quantities again after making changes. Up Hours and downtime must describe the time actually spent.

  3. Choose create report. The button changes to Creating report while processing. Creation recalculates and validates the report before saving it, including the material-stock and time checks.

Find the new PR record in Production Reports and check its Draft status, work order, product, shift, and output quantity. Open View details and compare the saved material quantities, lots, time, and supporting information with the values you intended to record.

For example, assume a package contains 20 finished units and a BOM material requires two component units for each finished unit. Reporting 10 packages gives 200 finished units and 400 component units for that matching material. The selected lot must support the calculated consumption. This example assumes the order's quantity-based method and per-unit requirement are correctly configured.

Continue with Confirm production report only after the saved draft and its manufacturing order are ready for posting.

If the calculation or save cannot finish​

Message or mismatchWhat to check
A weight-related error appears and there is no Actual Weight fieldCheck the order's consumption method. Use the standard create-report task for weight-based consumption.
A typed material Quantity changes after calculationCheck whether the material matches a BOM line. Matching lines are recalculated from the per-unit requirement and reported output. Review the order requirement and actual consumption before saving.
The calculated output differs from the counted unitsCheck Packaged quantity, the selected Packaging, and Unit of Measure. The report multiplies package count by the package definition's quantity.
A material lot has insufficient stockCompare the calculated material quantity with the selected lot. Correct an inaccurate input or select the lot actually used with sufficient inventory.
Up Hours or the total time is rejectedEnter productive time and downtime in hours, check that Up Hours is positive, and apply the configured maximum or exact-total rule.
A work order, work center, item, variant, packaging, unit, or warehouse is missingCheck the named reference. The selected work order and manufacturing order must provide valid context for calculation.

FAQ​

Business questions​

When should I use Create PR by quantity?​

Use it when the manufacturing order already calculates material consumption by quantity. Reported packages determine finished output, and matching BOM materials are calculated from their per-unit requirements. Use the standard create-report form when actual output weight drives material consumption.

Why must I still select the actual material lot?​

The per-unit requirement determines how much material is calculated, while Stock/Lot identifies the inventory used. Check its Lot Number, Unit of Measure, and saved quantity so the report traces the intended material and its stock sufficiency check applies to the correct lot.

Does saving this quantity report complete the manufacturing order?​

Saving creates a calculated and validated Draft report. Confirmation is separate: it completes the report and posts its time, inventory, and manufacturing-order effects. Review the saved quantities and material details before confirming.

Technical questions​

How does Packaged quantity become the report's Quantity?​

The calculation multiplies package count by the selected package definition's quantity. Ten packages of 20 units produce a report Quantity of 200 units. The Quantity beside the work-order details is separate manufacturing-order context.

Why can a material Quantity recalculate after I type it?​

For a material matching the order's BOM, the quantity-based calculation derives consumption from its per-unit requirement and report output. A typed value alone does not override that calculation. Review the recalculated and saved quantity; material outside the BOM retains its entered quantity.

Are Up Hours calculated from the quantity produced?​

No. Enter productive time in Up Hours and record interruptions separately in Downtime. The calculation uses those entered hours for output rates and labor cost. Check productive time plus downtime against the actual run and the configured reporting-hours rule.