Create production report

Create a production report to record a run's output, material lots, scrap, and time against a work order. Saving creates a Draft report for review. Confirmation is the separate task that completes the report and posts its time, inventory, and manufacturing-order effects.

Gather the run's results​

Have the work order, reporting date and time, shift, package count, actual weight, productive hours, material lot numbers, and any scrap or downtime details available. Use the results of the production activity you are reporting, rather than the full manufacturing order quantity by default.

The work order needs an active work center and a valid manufacturing order. The order supplies the product, variant, packaging, unit of measure, and warehouse. Missing packaging, an item unit, or the variant's weight unit can prevent calculation. Check that this setup represents the work performed before starting another report.

For weight-based consumption, also have the material blend percentages. The work center's blending approach and manufacturing validation settings affect the material calculation and permitted mix total. A quantity-based order uses its material requirements to calculate consumption instead.

Choose the work and reporting time​

  1. Open Manufacturing → Operations → Production Reports and choose Create production report.

  2. Select Work order. Check the displayed Manufacturing order, Product, Work Center, warehouse, and Unit of Measure. These values come from the selected work. If they describe another run, correct the work order selection before entering the results.

    The first Quantity, beside the work-order details, provides manufacturing-order context. The second Quantity, in Production Report, is the calculated output for this report. Keep these separate when the run produced only part of the order.

  3. Enter Manufacturing Date, including the date and time for the report. Check it against the activity you are reporting. On later confirmation, the report date supplies the starting point for the generated productive-time and downtime tickets, so the time matters as well as the calendar date.

Record output and time​

  1. In Production Report, select Shift and enter Packaged quantity. Read Packaging, the calculated Quantity, and Unit of Measure together. Package count and unit quantity can be different numbers.

    For example, if the selected package contains 20 units and the run produced 10 packages, enter 10 as Packaged quantity and check that Quantity is 200 units. These are illustrative values; use the selected package definition.

  2. Enter Actual Weight in pounds, as specified by the form. Keep usable output weight separate from scrap. The summary's Total weight shows Actual Weight; Total scrap weight records the calculated scrap amount separately. Review Over/under when the actual output weight differs from the expected weight for the reported quantity.

  3. In Time spent, enter Up Hours for productive time. Enter hours, rather than minutes: a seven-hour productive run is 7, not 420. Up Hours must be greater than zero.

  4. For interruptions, use Log downtime in Downtime, then enter Down reason, Hours, and Downtime description. Use Log additional downtime for another event. The report adds those line hours into Down Hours.

    Compare Up Hours plus Down Hours with the shift record. Manufacturing settings may require that total to equal a reporting limit, or stay within one. Do not put the entire shift in Up Hours and then add the same downtime again.

Identify materials and losses​

  1. In Raw Materials, select Stock/Lot for each material used. Check its displayed Lot Number, calculated Quantity, and Unit of Measure. Use Add raw material for another consumed lot. Choose the lot actually used so the report identifies the inventory behind the consumption.

  2. For weight-based consumption, enter Percentage Mix for the material lines. Review the calculated quantities after changing the output, weight, lot, or mix. This creation form displays the raw material Quantity as a calculated value. If it does not match the work performed, investigate the selected material, blend, and order requirements before saving.

    Mix validation follows manufacturing settings. It may require an exact 100% total, allow a configured tolerance, or omit the percentage check. The work center's blending method also affects which ingredients form the percentage basis. For quantity-based consumption, the calculation uses the order's per-unit material requirements instead of the weight-based mix check.

  3. If the run generated scrap, use Register scrap in Report scrap. Enter Scrap reason, Scrap quantity, and Scrap description. Use Add additional scrap for another loss. In weight-based reporting, the calculation distributes scrap across the raw materials using their mix percentages and converts the result to total scrap weight; the entered scrap quantity is not a substitute for Actual Weight.

    Where weight-based scrap or downtime is reported, each corresponding line needs a reason code and description. Keep those reasons specific enough to explain the loss or interruption when the report is reviewed.

Save and check the draft​

  1. Add Description of work and Comments where context helps explain the run. Use attachments to upload supporting files, such as an existing run sheet or photo. Check the attached file names before saving.

  2. Review the calculated output, material quantities, Down Hours, scrap, and Over/under. The summary's Actual Output Per Hour card reports weight per hour. Use a weight-based comparison for that card; see Production report for the quantity, weight, and rate calculations.

  3. Choose create report. The button changes to Creating report while processing. Creation calculates and validates the report before saving it. Resolve any returned errors and review the recalculated values before submitting again.

Find the saved report in Production Reports. Check its PR number, Draft status, work order, product, shift, quantity, and weight. Open View details and compare the saved materials, scrap, downtime, and attachments with the run information.

The draft is ready for review; creation has not completed its production posting. Use Confirm production report after checking that the report and its manufacturing order are ready for the stock, time, and order updates.

If the report cannot be saved​

Use the message to locate the input or reference that needs attention. Review the result after correction rather than changing unrelated values to make the message disappear.

Message or mismatchWhat to check
Work order cannot be found, or the work center is missing or inactiveCheck the selected work order and its assigned work center. Have the responsible planner correct that setup if it does not represent valid work.
Product, variant, warehouse, packaging, or unit is missingCheck the named record. The selected manufacturing order must supply valid product and packaging information; item and variant units support the calculation.
No raw materials providedCheck whether the manufacturing material policy requires raw materials, then complete the actual consumed lot lines.
Mix percentages do not satisfy the permitted totalReview the material rows, applicable blending basis, and configured exact-total or tolerance policy. Do not assume that every mode validates all visible percentages in the same way.
Scrap or downtime reason is missingComplete the reason and description on the affected line. Check for an unfinished additional row.
Up Hours is zero or total hours violate the limitCheck that productive time and downtime are entered in hours and are not counted twice. Apply the configured reporting-hours rule.
Actual weight is zero, or Over/under exceeds the permitted thresholdFor weight-based reporting, check the package count, actual output weight, variant unit weight, and material information. Investigate a real difference before changing values.
A material lot has insufficient stockCompare the calculated material quantity with the selected lot. Correct an inaccurate input or select the lot actually used with sufficient stock.

FAQ​

Business questions​

Does creating the report post production to inventory?​

Creation saves a calculated and validated Draft report. Confirmation is the separate task that completes it, creates time tickets and inventory movements, and records produced quantity against the manufacturing order. Review the draft before that posting.

Can I record a run that produced only part of the manufacturing order?​

Yes. Enter the packages, actual weight, materials, and time for that run. The work-order details show manufacturing-order context, while the Production Report section shows this report's output. Saving the draft does not reduce the order's remaining production balance.

Why do I need the actual material lot rather than only its product name?​

The selected Stock/Lot identifies the inventory behind the reported consumption. Check its Lot Number, calculated quantity, and unit of measure so the report traces the material actually used and the stock check applies to the intended lot.

Technical questions​

Why does the form show two different Quantity values?​

The Quantity beside the work-order details is manufacturing-order context. Quantity in Production Report is this report's output, calculated from Packaged quantity and the package definition. Compare the second value with the run you are recording.

Do I enter productive time and downtime in minutes or hours?​

Enter hours. Up Hours is productive time, and each downtime line's Hours contributes to Down Hours. For seven productive hours and one downtime hour, enter 7 as Up Hours and 1 on the downtime line; the combined reporting time is eight hours.

Must Percentage Mix always total exactly 100%?​

It depends on the manufacturing validation settings and consumption approach. Weight-based reporting can use an exact 100% rule, a configured tolerance, or no percentage validation; the blending method affects the percentage basis. Quantity-based consumption skips that weight-based mix check and calculates material quantities from the order's requirements.