Production Reports records what a production run reported: output, material and weight information, up/down hours, and its manufacturing order, operation, resource and shift. Use the list to prepare reports, inspect differences, confirm a checked Draft, and keep supporting files with completed work.

Open Manufacturing → Operations → Production Reports.

Start with the run and its status​

Match Report number, Manufacturing order, Product, Work Center, Work order, and Shift to the run being reviewed. Use View details to inspect the record behind the row.

Read Quantity and Packaging quantity with their product and package basis. Compare weight with Planned Weight, and review Total scrap weight, Scrap Rate, Up Hours and Down Hours as separate concerns. The production-report explanation explains the supported calculations and flags.

Prepare and review a report​

Use Create production report for a new run. Saving creates a Draft for review. Use Update production report when the list offers Update for Draft or Confirmed.

Before confirmation, compare the reported output with the physical result, check the selected center/shift/operation, and inspect the material and weight differences. Review Output Level and Over/Under Thresholds together with the values that produced them. Resolve an unexpected result before proceeding.

For orders already using quantity-based calculation, the quantity-reporting task provides the appropriate alternative entry point.

Confirm and verify effects​

The row action confirm is shown for Draft. Follow Confirm production report to review the required context and consequences. Successful confirmation completes the report; do not assume an intermediate Confirmed stage is required.

Check Completed, output quantity, linked time/inspection information and the parent manufacturing order’s progress. Investigate a missing warehouse location, inconsistent mix or output-level rejection using the precise error and relevant record settings.

For an already Completed report, use Attach a file for supporting evidence. Verify the file on the intended report after saving. Use the Production Report Calendar when reviewing reports by resource and recorded dates.

FAQ​

Business questions​

What work belongs in Production Reports?​

Use it to record and review a production run’s output, time, material/weight information and context, then confirm a checked Draft and retain supporting evidence.

How do I avoid reviewing the wrong run?​

Match report number, manufacturing order, product, work center, work order and shift together, then open View details.

What should I check before confirmation?​

Compare physical output and package basis, selected production context, material/weight differences, up/down hours and the output/threshold flags.

Technical questions​

Does confirmation require a separate Confirmed step?​

No. The Draft confirm action completes the report on success. Check the saved Completed status and its connected results.

When does the list offer Update or Attach File?​

Update is shown for Draft and Confirmed reports. Attach File is shown for Completed reports; use the corresponding task for its checks.

Are Packaging quantity and Quantity interchangeable?​

No. Packaged quantity counts packages; output quantity uses the package size. For example, 10 packages containing 20 units each represent 200 output units.