Update manufacturing order

Update a Draft manufacturing order when its production quantity, material plan, routing, dates, or project information needs to change. Saving recalculates the plan on the same order and keeps its ordered quantity aligned with the revised requirement.

Use this task before confirmation. It does not allow direct updates to a subassembly order or changes to the manufactured item, variant, or warehouse.

Check which order you can update​

Open Manufacturing → Operations → Manufacturing Orders. Match the order number, item name, warehouse, and Sales order to the requirement you intend to change. Check that Status is Draft; the row's Update action appears in that state, and saving also checks the state.

Check Parent manufacturing order and Root manufacturing order when the order belongs to related production work. A subassembly is derived from its parent's routing requirement. Open the root order to change the plan; a direct subassembly update is rejected even when that subassembly is Draft.

Before changing a root order, check its related subassembly states. A Draft parent cannot be replanned while the subassemblies feeding it have moved beyond Draft. Review any orders named in the error before trying again.

Make the supported changes​

  1. Choose the row's Update action to open Update Manufacturing Order. On Basics, confirm the loaded product and location before editing.

  2. Keep the manufactured item and variant unchanged. If you adjust the packaging, select it for that same item and variant, then check the quantity against its size. A sales-linked order must still match the linked line's product, variant, packaging, unit, and attributes.

  3. Keep warehouse and the existing Sales order association. This update rejects a warehouse change and a new or different sales order selection. For a different finished item or variant, create a manufacturing order for the correct product and review the incorrect draft separately.

  4. Change the production requirement using the inputs below. Check the recalculated values after each material change to the plan.

    InputHow to make the choice
    QuantityEnter a positive amount in the item's unit of measure, aligned with the selected packaging size. This revises the Draft order's total requirement as well as its remaining quantity.
    Order date and Shipping start dateKeep both dates populated, with order date on or before shipping start. Review the calculated production dates after changing either.
    Bill of MaterialsChoose the recipe for this run. A different BOM replaces the order's raw-material lines with that recipe, so select it before making order-specific material adjustments.
    RoutingChoose the operation plan for the item. Recalculation loads the selected routing's steps again; review Routing steps and operations before saving.
    Preferred work centerRecord the intended preference among the centers offered for the warehouse. Check the availability messages alongside it before accepting the plan.

Check the recalculated materials and dates​

In Raw Materials, compare each Raw material, Quantity, Unit of Measure, Packaged quantity, and Packaging with the revised requirement. Use Add additional raw material, or Add raw material for an empty list, when this run needs another component. The table also permits a line to be removed.

With the same BOM selected, the order keeps its own material lines. A quantity-based recipe scales those line quantities when the order quantity changes. Percentage-based recipes can derive quantities from the finished product's weight and Percentage Mix; percentage-and-quantity recipes use the mix on initial selection, then scale existing quantities on later order-quantity changes. Check the results after editing a quantity or mix. Selecting a different BOM discards the previous line set, including order-specific adjustments.

For example, assume a quantity-based Draft order is for 120 pieces, packaging contains 12 pieces, and its current material requirement is 30 kilograms. Increasing Quantity to 180 requests 15 packages and scales that material to 45 kilograms. These are illustrative values and assume the same BOM, packaging, and proportional recipe.

Review Planned start date, Planned end date, and Production Due Date. Planned start is shipping start minus the configured minimum production lead time, bounded by the order date. Planned end adds the calculated manufacturing minutes, and production due date follows planned end. Read the routing and work-center availability messages and compare the resulting end with the delivery commitment. Production end can fall after shipping start.

Use project information to update project name, Project description, and Notes when the run's context changes. Internal barcode is available on Basics. For a linked sales order, account and sales references are refreshed from that order when saving; check the existing sales association rather than using the form to reassign the run.

Saving a revised root order can add, resize, or remove Draft subassembly manufacturing orders. Manufactured input parts declared by the routing qualify for linked production when they have an active BOM and active routing. Their quantities follow the revised parent requirement.

If the routing no longer requires an input part, saving removes its obsolete Draft subassembly branch, including its dependent Draft subassemblies. Check this consequence before changing the routing. If a related order has moved past Draft, the reconciliation is blocked rather than unwinding that production work.

Save and verify the result​

  1. Recheck the revised quantity, packaging, material lines, routing, dates, and related subassembly scope. Resolve calculation errors before saving.
  2. Choose Update order. The button shows Updating order while the request is processed.
  3. Look for Manufacturing order successfully updated. Locate the same order number in Manufacturing Orders and confirm that Status remains Draft.
  4. Compare Total Quantity and Quantity remaining with the revised amount. Check Packaged quantity, Order date, Shipping start date, and the sales reference against the intended plan. Reopen Update to inspect the saved material lines, selected routing, and calculated dates when those were changed.
  5. Review the linked subassembly orders using their Parent manufacturing order and Root manufacturing order references. Check that quantities and remaining branches match the revised routing requirement.

The update also runs the order's cost calculation. For Draft orders, that calculation clears planned cost and planned cost per unit to zero, along with planned weight and planned material/labor cost figures. A zero Draft planned cost does not establish that production has no cost. Use the material, quantity, routing, and date checks to verify this draft.

If saving is blocked​

ProblemWhat to check
Order is no longer DraftRecheck its current status. This task cannot edit an Open, In Progress, Completed, or Canceled order.
Cannot update a subassembly directlyOpen the root manufacturing order named in the message and review its production requirement.
Related subassemblies have moved past DraftReview the orders and states named in the message before replanning the root. Its Draft state alone does not establish that related work can be changed.
Cannot change item or variantKeep the original identity. Create a separate order for the intended product and review the incorrect draft separately.
Warehouse or sales-order change rejectedRestore the existing warehouse or sales association. A visible selector does not make reassignment part of this update.
Quantity is zero, negative, or does not fit packagingEnter a positive multiple of the packaging size and check the resulting packaged quantity.
Missing or invalid BOM, routing, product unit, or variant weight unitCheck the relevant item or manufacturing definition. Correct the setup, then return and review the recalculated plan.
Date or scheduling errorCheck order date, shipping start, warehouse/site setup, routing durations, and the availability messages. Recheck the calculated dates after correcting the cause.

After an error, reopen the same order and check the saved values before repeating the update. A success message and the saved record checks establish the result; leaving the form does not establish that the revision was saved.

Read the manufacturing order explanation to interpret total, remaining, and produced quantities. Use the BOM to check the recipe basis and the routing to understand the operation plan.

FAQ​

Business questions​

When can I update a manufacturing order?​

Use Update while the order is Draft. Direct subassembly updates are blocked; edit the root order's plan instead. Related subassemblies must also remain Draft for that plan to be reconciled.

Can I use Update to manufacture a different item or variant?​

No. Saving rejects a change to the manufactured item or variant. Create an order for the intended product and review the incorrect draft separately.

What happens to subassembly orders when I revise the root plan?​

Saving reconciles the related Draft production requirements. It can create missing subassembly orders, revise their quantities, and remove obsolete Draft branches when the routing no longer requires them. Related work beyond Draft blocks this reconciliation.

Technical questions​

Why did changing Quantity also change Total Quantity and material amounts?​

For a Draft update, the revised quantity becomes the ordered-quantity baseline shown as Total Quantity. Material amounts recalculate according to the BOM's consumption strategy. Check both product units and packaged quantity, then review each material's resulting amount.

Will updating the order preserve my material-line adjustments?​

Keeping the same BOM preserves the order's line set, although quantity and mix rules can still recalculate amounts. Selecting a different Bill of Materials replaces those lines from the new recipe. Choose the BOM before making order-specific adjustments.

Why is planned cost zero after updating the draft?​

The cost calculation clears planned cost and planned cost per unit for Draft orders. It also clears the planned weight and planned material/labor cost figures. Zero in these Draft fields does not mean the materials or work are free; verify the draft's quantities, recipe, routing, and dates.