Update work center
Correct an existing resource’s standing settings while keeping its name/code and production context clear.
Open Manufacturing → Configuration → Work Centers.
Prepare the resource definition
Have the resource’s code/name, warehouse, site, classification, daily availability, item output rates, time standards, cost rates, and reporting limits ready. Read the work-center explanation for how these values fit together.
Keep the quantity basis visible: daily availability uses hours; setup, cleanup, and changeovers use minutes. Output per hour must be read with its product and unit. Cost per hour, fixed cost, cost per unit, and idle cost per hour are separate rates.
Update work center
- Find the intended center and choose Update. Compare its code and name before changing the definition.
- On Basics, set Work center code, Work Center Name, warehouse, Work site, Work Center Type, and Description. Review Available hours per day and Barcode component code.
- On Capacity, review the setup/cleanup and changeover standards. For each output row, check the item, Product, Attributes, Output per hour, and Unit of Measure. Check minimum scheduled quantities separately from hourly rates.
- Review item-to-item changeover entries as directed pairs: From item, To item, and Changeover time (min).
- On Costing, review Cost per hour, Fixed Cost, Cost per unit, and Idle cost per hour on their own bases.
- On Machine settings, choose Machine blending mode to match how the line receives and blends material. On Reporting, review under/over-reporting warning/error levels and rejection/rework limits; keep warning levels separate from error levels.
- Compare the complete definition with the intended resource and choose Update Work Center.
Check the saved resource
Reopen Update on the saved name/code. Compare the site, warehouse, classification, daily hours, capacity rows/units, time standards, rates, blending mode, and reporting thresholds with your intended setup. Correct a wrong saved value and repeat the comparison.
For a dated interruption, use Log downtime. Keep a maintenance period separate from the resource’s standing configuration.
FAQ
Business questions
When should I create or update a work center?
Create a separate record for another production resource. Update the existing record to correct its identifying details, capacity, time standards, rates, or reporting settings.
How do site and work center type differ?
Work site identifies the production facility. Work Center Type classifies the resource by function. Check both alongside the individual center’s name and code.
Should I use setup editing to record a dated outage?
Use Log downtime for a dated interruption. It creates a maintenance work order; the configuration form defines the center’s standing settings.
Technical questions
Which time units should I compare?
Available hours per day uses hours. Default setup, cleanup, and changeover values use minutes.
How should I read an output-capacity row?
Read item, Product/variant filters, Attributes, Output per hour, and Unit of Measure together. A rate for one product/unit is a different assumption from another.
How do I verify the saved settings?
Reopen Update on the intended name/code. Compare location/type, daily hours, capacity rows and units, timing standards, rates, blending mode, and reporting thresholds with your intended definition.