Log downtime

Use Log downtime to record a dated interruption at a work center, such as planned maintenance, equipment failure, or a changeover. Saving creates a maintenance work order for the chosen period. The work-center status stays unchanged.

Prepare the outage period​

Open Manufacturing → Configuration → Work Centers and identify the resource by its name, code, site, and type. Log downtime is shown for centers with Active status.

Have a start and end date and time ready. Both are required, and the end must be later than the start. The dates must be on the current UTC day or later. This action rejects an outage from an earlier UTC day, even when your local calendar date differs.

Check work orders scheduled at that center during the proposed interval. An overlap prevents the maintenance entry from being saved. For Draft/Open production work, use the update task to arrange a different slot before submitting the outage. If an In Progress, Completed or Maintenance record overlaps, ask the production planner to review the conflict; this task provides no reversal or rescheduling procedure for those states.

Choose a Downtime reason that describes why production will be interrupted. Use Downtime description for the practical detail your team needs. For example, select PM - Planned Maintenance for approved maintenance booked in advance, then describe the equipment or work involved. The reason and description are optional, but they help explain the saved maintenance entry.

Register the outage​

  1. In the selected work center's row, choose Log downtime. The Register Downtime for Work Center panel opens.
  2. In Work Center Summary, compare Work Center, Code, Site Location, and Work Center Type with the intended resource. Correct the selection before entering an outage for a different center.
  3. Under Outage information, select Downtime reason and add Downtime description as needed. Distinguish the cause from the detail: for example, EF - Equipment Failure identifies a breakdown, while the description explains which equipment failed.
  4. Enter Start date and End date, including the times. Check the interval, the current UTC-day restriction, and the center's scheduled work before submitting.
  5. Choose Log Outage. The button reads Logging Outage while the request is being processed. If a validation message appears, correct the issue using the checks below before trying again.

Check the maintenance work order​

Open Manufacturing → Operations → Work Orders and locate the new entry for the selected center and outage period. Compare Work Center, Start date, and End date with the information you submitted. The entry has Maintenance status and type. Planned Time is the length of the outage.

For example, an outage on a future UTC day from 13:00 to 14:30 creates a 90-minute maintenance interval. Check that the saved entry identifies the intended center and the same start and end.

Logging the outage creates the maintenance work order. Overlaps must be resolved before the outage can be registered. Draft/Open production work can be rescheduled through Update; other states need planner review. Check the saved maintenance entry when verifying success; the work-center record retains its existing status.

Resolve a rejected outage​

Message or situationWhat to check and correct
End date must be after start dateEnter an end later than the start. Equal timestamps do not create a valid interval.
Start date must be today or in the futureCompare the start with the beginning of the current UTC day. An earlier UTC date is rejected.
End date must be today or in the futureCheck the end against the same UTC-day boundary, then confirm it is later than the start.
Conflicting work orders foundReview work orders at the same center whose dates overlap the outage. Reschedule Draft/Open production work through Update and verify its new dates. Refer other states to the production planner before retrying.
Work center not foundReturn to Work Centers and select the intended existing record again.

For the 13:00–14:30 example, a work order scheduled from 14:00 to 15:00 overlaps the outage. If that work order is Draft/Open, use Update to move it outside the proposed outage; refer other states to the production planner before retrying Log Outage. Check the revised schedule before retrying so the maintenance entry represents the time your team has agreed to reserve.

For the meaning of resource states, capacity settings, and related records, read Work center.

FAQ​

Business questions​

Can I use Log downtime for planned maintenance?​

Yes. Choose PM - Planned Maintenance for approved maintenance booked in advance, enter the start and end, and add the practical details. Saving creates a maintenance work order for that center and period.

Does logging an outage change the work-center status to Downtime?​

No. This action creates a maintenance work order and keeps the work-center record's status unchanged. Verify the saved maintenance entry in Work Orders using its center and dates.

How should I use the reason and description together?​

Use the reason to identify the cause, such as equipment failure, planned maintenance, labor, or supply. Use the description for the specific equipment, work, or circumstances. Both are optional and are carried onto the maintenance work order when supplied.

Technical questions​

Why is Log downtime missing from a work-center row?​

The action is shown for Active work centers. Check the row's status and review what that state means before changing the resource's availability.

Can I log an outage that started on an earlier day?​

The start and end must be on the current UTC day or later. An earlier UTC day is rejected. The end must also be later than the start, so check both dates and times before submitting.

How do I resolve Conflicting work orders found?​

Check work orders at the same center and compare their dates with the outage. Reschedule Draft/Open production work through Update, then verify its saved dates. Refer other states to the production planner; this task does not provide a reversal for them. Retry only after resolving the overlap.