Skip to main content

Scrap Orders

Use Inventory → Scrap → Scrap Orders to prepare and review a stock write-off, correct its Draft, and investigate the resulting movement. The intended movement takes the selected quantity from the warehouse's stock location to its scrap location.

Keep the proposal, stock movement, and financial result as separate checkpoints. Saving a Draft does not deduct stock. A later Completed order label alone does not establish that the expected stock and accounting results are present.

This Inventory process concerns existing stock selected for scrapping. Manufacturing scrap recovery, which converts material into a recovered product, is separate work.

Check the source before preparing the order​

Identify the exact warehouse and source stock. Compare the product, variant, packaging, unit, lot, available quantity, and cost layer with the goods selected for the write-off. A matching product name is not enough to establish the source.

The warehouse must be active and have a stock location for calculation. Completion also needs its scrap location and source stock with a general-ledger account. Usable units of measure must exist so quantities can be interpreted correctly.

Prepare Scrap Date for the event and Posting date for the intended accounting date of the later movement. Keep the reason and supporting references in Notes. Use a positive quantity in the source stock's displayed unit; it is the amount selected for scrapping, rather than a new remaining balance.

For lot- or serial-identified stock, keep the order in review until the inventory lead has checked the source identity and how that source will be deducted. A lot number displayed on the Draft is not, by itself, proof of the source used by the resulting movement.

Prepare or correct the Draft​

Record the proposed write-off​

Use Create scrap order when no proposal exists for this event. Choose the warehouse before selecting stock, then review each line's unit, quantity, availability, and value. The final Create scrap saves a Draft with an SC order number.

Find that number in Scrap Orders. Compare its warehouse, Scrap Date, Posting date, Status, and Scrap note with the proposal. Reopen its lines with Update to check what was saved before treating it as ready for further work.

Reconcile quantity and cost before proceeding​

Calculation compares the requested quantity with the selected stock's availability. If the request is too high, it reports the difference and reduces the quantity to the available amount. Review the returned quantity: accepting the reduction may record a different write-off from the one intended.

Cost per unit comes from the source stock. Total value of scrap is quantity to scrap × cost per unit, rounded to five decimal places. Recalculation can refresh both availability and cost, so a saved Draft needs another review if stock activity has occurred while it was waiting.

Use Update scrap order to correct a Draft's lines, dates, warehouse, or notes. The Update row action is offered for Draft orders; Update order saves the revised proposal. Reopen the same SC order and compare the saved lines with the intended correction.

If the warehouse changes, reselect every source line for that warehouse. Do not assume that a warehouse change replaces previously selected stock. Check lot, unit, availability, and cost again.

Remove a proposal that is no longer needed​

The Draft row also offers Delete. Use it only when the proposal should be removed, rather than corrected. Check the SC order number before confirming Delete in the Delete Stock Order dialog; the deletion is irreversible. Deleting a Draft is not a reversal of a stock movement or financial posting.

Review the completion handoff​

Completion is a separate stock-changing stage. The Draft row offers complete. Its confirmation is titled Mark Scrap Order as Completed, warns that available stock will decrease, and has a final complete control. Treat this as a request to post the write-off, rather than a way to save a proposal.

Before this handoff, check the current source availability, the saved positive quantities and costs, the warehouse's stock and scrap locations, and the date intended for accounting. Resolve any source identity or lot discrepancy with the inventory lead before proceeding.

The completion action uses the saved lines to build a stock-to-scrap movement, requests movement completion, and marks the order Completed. These results need separate checks. If an order already has a movement, is Completed, or has an uncertain previous result, inspect that work before another attempt or a replacement order.

Check progress and the actual result​

Use the Scrap order explanation to interpret the record. Read its status alongside the source stock and corresponding movement:

CheckpointWhat it tells youWhat to check next
Draft savedThe proposed stock, quantity, dates, and reason have been recorded.Reopen the lines, reconcile current availability and cost, and correct any difference.
Completion requested or its result is uncertainStock-changing work may have started.Find any movement referring to the SC order number before repeating an action.
Order shows CompletedThe order's completion action reached its status update.Check the movement, signed stock history, and financial result independently.
Movement and history agree with the intended write-offThe actual source, destination, quantity, and cost can be reconciled.Retain the references and have the relevant financial posting checked.

Find the Movement that refers to the Scrap Order number. Compare its stock source and scrap destination, warehouse, item configuration, lot, actual quantity, and cost with the order. Check that the source being reduced is the intended source, especially for lot or serial stock.

In Movement History, compare the negative source entry with the positive scrap-destination entry for the same movement. History records changes; use current stock information to establish the remaining balance. A general-ledger reference or Completed label does not replace a check of the actual financial posting.

Resolve a changed or uncertain case​

SituationWhat to do before continuing
Quantity was reduced during calculationCompare the returned amount with availability and the intended write-off. Correct the Draft rather than accepting an unexplained change.
Warehouse or source stock changedReselect the source lines for the intended warehouse, then review unit, lot, quantity, and cost.
A required location, stock record, or account is missingHave the warehouse and source setup checked. Do not substitute a different source solely to get past the message.
Update or complete is missingCheck Status. These row actions are offered for Draft; investigate a Completed or uncertain result through its movement and history.
A lot, quantity, or location differs in the movementKeep the original order and stock references, and have the inventory lead investigate the actual deduction before further scrapping.
Completion failed, no movement is found, or results disagreeInspect existing records and retain the error and SC number. Check stock and finance results before retrying or arranging a correction.

Example: keep proposal and result separate​

Assume the intended write-off is 8 units from stock with 30 units available at 2.50 per unit. These values are illustrative. The reviewed Draft should carry 8 × 2.50 = 20.00.

If 35 units were requested, calculation would reduce the quantity to 30 and the value would become 75.00. Correct the proposal to the intended 8 units before saving. Creating or updating that Draft does not establish a remaining balance of 22.

If completion is later requested, compare the actual movement and history with the intended −8 units at the source and +8 units at the scrap destination. A source balance of 22 follows only if the correct source was reduced by 8 and no other stock activity occurred. Have the financial result checked separately against the movement's actual quantity, cost, and accounting date.

Hand off the checked references​

Keep the SC order number, source stock and lot references, movement number, dates, quantities, costs, reason, and any unresolved message together. This lets the inventory and finance owners reconcile the same event. An uncertain result remains an investigation; do not describe the write-off as finished solely because its order is Completed.

FAQ​

Business questions​

When is a Draft ready for the next stage?​

When its saved source stock, warehouse, positive quantity, unit, dates, reason, and calculated cost match the intended write-off, and current availability has been reviewed. Resolve location, account, and source identity issues before the completion handoff.

Can I correct the proposal before stock is scrapped?​

Yes. The Draft row offers Update for correcting lines, dates, warehouse, and notes. Update order saves the proposal without performing or reversing a movement. Reopen the same order to check the saved correction.

Does Completed prove that the write-off and accounting are correct?​

No. Compare the corresponding movement and signed history with the intended source, scrap destination, quantity, lot, and cost. Check the actual financial result separately before closing the work.

Technical questions​

Why can the proposed quantity change during review?​

Calculation uses the selected stock's available quantity. A request above availability is reported and reduced to that available amount. Reconcile the returned quantity with the intended write-off before saving or proceeding.

How is the proposed scrap value calculated?​

Multiply quantity to scrap by the cost per unit copied from the selected source stock, then round to five decimals. Recalculation can refresh that cost; 8 units at 2.50 gives a proposed value of 20.00.

What extra check is needed for lot or serial stock?​

Have the inventory lead check the exact source identity and how it will be deducted before proceeding beyond the Draft. Then compare the actual movement and source history with that identity; the lot displayed on the proposal alone does not establish the deduction.